FEMA Bidding Process agraham alec.coop (17 Dec 2020 19:23 UTC)
RE: FEMA Bidding Process Michael Callahan (17 Dec 2020 22:01 UTC)

FEMA Bidding Process agraham alec.coop 17 Dec 2020 19:23 UTC
Good morning,

I am looking for a little help with the FEMA bidding process.  We are told that all bids must be made using unit pricing.  Has anyone procured bids approved through FEMA using another type of bidding?  For example, per FEMA guidance, T&M without a ceiling price has a high risk of noncompliance. How do they feel about capping T&M, or is there another method?  If we have to bid everything by unit pricing, we are estimating approximately 800 to 1000 separate bids.

Any help is appreciated.

Thanks,

Aarron Graham
Director of Loss Control
Association Of Louisiana Electric Cooperatives
10725 Airline Hwy
Baton Rouge, La 70816
225-293-3450 ext.13
Cell 225-936-2489
agraham@alec.coop<mailto:agraham@alec.coop>