OCR Maintenance Schedule Matthew Avery (12 May 2023 09:46 UTC)
RE: OCR Maintenance Schedule Mike Grice (12 May 2023 13:27 UTC)
RE: [External]OCR Maintenance Schedule Michael Roberge (12 May 2023 14:33 UTC)
Re: EXTERNAL: OCR Maintenance Schedule Daniel Powell (12 May 2023 14:50 UTC)
RE: EXTERNAL: OCR Maintenance Schedule Jeff Brewer (12 May 2023 18:52 UTC)
RE: OCR Maintenance Schedule Kurt Miller (12 May 2023 15:02 UTC)

RE: [External]OCR Maintenance Schedule Michael Roberge 12 May 2023 14:33 UTC

Matt-
We used to do an annual oil sample and test the dielectric.  Assuming it was good we used 64 operations or 3 years in service (whichever came first as our targets)-we mostly had type L reclosers.  I am pretty sure this was developed from the Manufacturer recommendations.  I know many Coops stretch the years out to match other maintenance cycles, but we tried to follow the factory recommendations.

  TGIF!

-----Original Message-----
From: engineering@feca.simplelists.com <engineering@feca.simplelists.com> On Behalf Of Matthew Avery
Sent: Friday, May 12, 2023 5:46 AM
To: FECA-ENG ListServ <engineering@feca.simplelists.com>
Subject: [External]OCR Maintenance Schedule

This is an EXTERNAL email. Exercise caution. DO NOT open attachments or click links from unknown senders or unexpected email.

Good morning.

We are re-evaluating our OCR maintenance schedule. Currently, we replace all OCRs on an 8 year cycle.

What is your maintenance/replacement schedule?

Thanks,

J. Matthew Avery
SVP of Engineering & Operations
CHELCO